Which of the following statements is true about velocity?
A) The customer sets the velocity of each scrum period.
B) When a project begins, the senior team members guess the velocity of the team.
C) After a scrum team commits to requirements in a scrum period, it estimates the velocity it can achieve.
D) A team should approach the scrum master to change the order of the requirements it has committed to.
Correct Answer:
Verified
Q3: _ is the only person on a
Q7: Which of the following is an advantage
Q10: According to scrum essentials,the first step of
Q13: Designing only the portions of the system
Q15: Which of the following statements indicates why
Q18: According to the systems development life cycle
Q20: The systems development life cycle (SDLC) gained
Q35: Which of the following development methodologies is
Q36: In _,two members share the same computer
Q42: Which of the following is a characteristic
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents