According to Brooks' Law,adding more people to a late project ________.
A) makes the project later
B) decreases the overall cost
C) improves the quality of work
D) enhances the team's productivity
Correct Answer:
Verified
Q2: The initial step in the first phase
Q3: As development teams become larger,the average contribution
Q5: The primary purpose of the requirements analysis
Q5: The process of creating and maintaining information
Q6: As staff size increases,_.
A)the average contribution per
Q7: Adding more people to a late systems
Q8: _ feasibility concerns whether the new information
Q9: Developers in the _ phase of the
Q10: The bigger the system and the longer
Q11: _ are IT professionals who understand both