After fixing the plane table to the tripod, the main operations which are needed at each plane table station are
i. levelling
ii. orientation
iii. centering
The correct sequence of these operations is
A) (i) , (ii) ,.(iii)
B) (i) , (iii) , (ii)
C) (iii) , (i) , (ii)
D) (ii) , (Hi) , (i)
Correct Answer:
Verified
Q9: The process of determining the locations of
Q10: The instrument used for accurate centering in
Q11: The two point problem and three point
Q12: The resection by two point problem as
Q13: The methods used for locating the plane
Q15: 90°Bowditch rule is applied to
A)an open traverse
Q16: If in a closed traverse, the sum
Q17: If the reduced bearing of a line
Q18: The angle between the prolongation of the
Q19: Transit rule of adjusting the consecutive coordinates
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents