As a Foreign Service Officer you are responsible for determining the cumulative effect of several delays in a project. You have access only to the project's bar chart. Which of the following outcomes can be predicted?


A) The cumulative delay cannot be calculated by reviewing only the bar chart because bar charts do not show relationships among activities
B) The cumulative delay is simply the sum of the individual activity delays
C) The cumulative delay can be calculated by adding up the delays in the critical activities, only
D) The cumulative delay cannot be calculated by reviewing only the bar chart because bar charts do not show the duration of all activities

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents