Brendan is managing a large IT project at a venture-backed startup that is scaling up. The project requires frequent change requests due to multiple IT initiatives simultaneously happening within the growing firm. A particular business manager with a lot of clout is pressing Brendan to make changes that may not only impact the project's scope, but cost and timeline as well. Which exemplifies the best route for Brendan to take?
A) He could use corrective action.
B) He could suggest the formation of a change control board.
C) He could employ dynamic programming.
D) He could hold a kickoff meeting.
E) He could consult the scope creep committee.
Correct Answer:
Verified
Q134: Doris Mayweather is managing the execution of
Q135: In which phase is the infrastructure for
Q136: Which process group does performance reporting belong
Q137: Which is NOT part of the Integrated
Q138: What is the BEST way to notify
Q140: Which is NOT an input to the
Q141: Which is NOT an output of the
Q142: Which is NOT an input to the
Q143: Which is NOT part of the Scope
Q144: Which is NOT an input to the
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents