Suppose task B follows task A. The likelihood that a problem will occur with task A is 0.5, and the time to correct the problem would be 2 months. The likelihood that a problem will occur with task B is 0.2, and the time to correct the problem would be 3 months. The risk consequence of both activities combined is (circle one) :
A) 3.5 months
B) 5.7 months
C) 1.6 months
D) cannot be determined
Correct Answer:
Verified
Q1: Which of the following is the first
Q2: If the risk likelihood is 0.4, the
Q4: The concept of project risk is a
Q5: Which of the following are sources of
Q6: Which of the following are common techniques
Q7: Risk checklists (circle all that apply):
A) List
Q8: A cause and effect diagram is ordinarily
Q9: Risk likelihood is (circle all that apply):
A)
Q10: When applying a design margin, the target
Q11: A system prototype is (circle all that
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents