With a Firm Fixed Price Contract (FFP)

Question 22

Multiple Choice

With a Firm Fixed Price Contract (FFP)


A) the customer assumes the risk of cost overruns
B) the price to the customer remains the same
C) the contractor is assured of being reimbursed for all allowable expenses
D) contractor risks underestimating the cost and losing money on the project
E) cutting-corners to reduce costs is a potential risk