Solved

The Following Chart to Answer Questions (A) Through (E)

Question 38

Essay

The following chart to answer questions (a) through (e). Suppose the project is currently at the end of month 4.
The following chart to answer questions (a) through (e). Suppose the project is currently at the end of month 4.    a) When was the project originally scheduled for completion? (b) What was the original budgeted cost of the project? (c) As of month 4, how far (in months) is the project behind schedule in terms of the value of work completed? Show on the chart how this is determined. (d) As of month 4, what is the forecast cost to complete the project, and the forecast cost at completion? (e) As of month 4, what is the revised completion date for the project? Indicate this and the forecast cost at completion on the chart. a) When was the project originally scheduled for completion?
(b) What was the original budgeted cost of the project?
(c) As of month 4, how far (in months) is the project behind schedule in terms of the value of work completed? Show on the chart how this is determined.
(d) As of month 4, what is the forecast cost to complete the project, and the forecast cost at completion?
(e) As of month 4, what is the revised completion date for the project? Indicate this and the forecast cost at completion on the chart.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents