Activity X Has Four Immediate Predecessors, Three of Which Finish

Question 4

Multiple Choice

Activity X has four immediate predecessors, three of which finish before their late finish date, one that finishes after its late finish date. What effect will this have on Actiivity X (circle one) :


A) it will be delayed
B) it will be delayed only if the late predecessor is on the critical path
C) it will be able to start early if any of the early predecessors are on the critical path
D) none of these