Activity X has four immediate predecessors, three of which finish before their late finish date, one that finishes after its late finish date. What effect will this have on Actiivity X (circle one) :
A) it will be delayed
B) it will be delayed only if the late predecessor is on the critical path
C) it will be able to start early if any of the early predecessors are on the critical path
D) none of these
Correct Answer:
Verified
Q1: The EV represents, at a given time:
A)
Q2: Suppose a project was originally estimated to
Q3: Which of the following might project managers
Q5: To implement a time buffer (circle one):
A)
Q6: Five days after starting a work task,
Q7: Among important ways to assess the status
Q8: Which of the following are true about
Q9: In controlling projects, data on actual project
Q10: Often, the impact of changing system requirements
Q11: Ways to control the adverse impact of
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents