A contingency amount can be (circle one) :
A) applied to individual activities or work packages
B) applied to the project as a whole
C) continually increased to cover cost escalation
D) all of the above
E) a and b only.
Correct Answer:
Verified
Q2: If the target cost is $235,000, which
Q3: If the actual cost turns to be
Q4: Which method relies on formulae and tables
Q5: Which method provides the least accuracy when
Q6: The estimate providing the best accuracy for
Q8: Which of the following are potential ways
Q9: The project planning and estimating process (circle
Q10: Life cycle costs (circle all that are
Q11: Which of the following statements are true
Q12: Statement: Cost escalation always results in the