Question 53

Multiple Choice

At the end of 2012 Funtime provided the following information about the project:  Costs incurred  Estimuted rast  Year  to dnte  remainine 2012$1,200,000$600,000\begin{array} { l l l } & \text { Costs incurred } &\text { Estimuted rast } \\\underline{\text { Year }} & \underline{\text { to dnte } }&\underline{ \text { remainine } }\\2012 & \$ 1,200,000 & \$ 600,000\end{array}

What percentage is playground complete?


A) 62.5%
B) 66.7%
C) 55.6%
D) 50.0%