Characteristic of a Critical Path Schedule is
A) there can be float on all but the critical path itself
B) only the critical portion of the project is what is shown so everyone can concentrate on that section
C) it eliminates the need for Constructive Acceleration
D) it eliminates the need for directed acceleration
Correct Answer:
Verified
Q3: Without a change order clause in the
Q4: In most cases, a flaw or ambiguity
Q5: Until one knows otherwise
A) the Contract Administrator
Q6: If a change affects the schedule
A) the
Q7: Constructive changes
A) have a positive effect on
Q9: The Eichleay formula was developed for
A) private
Q10: Sometimes the requirements of proof and detail
Q11: The Owner can grant to an agent
Q12: Constructive changes can seemingly be clarification of
Q13: Ambiguities will always be ""construed against the
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents