A CM at Risk
A) has safety violations that need to be addressed
B) must be bonded on the project
C) will need to closely analyze design and construction related to a Guaranteed Maximum Price
D) can escape risk by passing it on to the Constructor
Correct Answer:
Verified
Q5: Multi-prime Contracting
A) is hazardous
B) usually improves the
Q6: Design Builders
A) are not commonly found except
Q7: IPD
A) stands for Important Project Directive and
Q8: PPP
A) stands for Private Public Partnership
B) puts
Q9: BIM
A) is Building Information Management
B) is best
Q11: IPD relies upon full and open communication
Q12: PPP stands for Private Public Partnership
Q13: The expertise of each party is to
Q14: In Design-Bid-Build, the Owner usually has a
Q15: Desig-Bid-Build is a way for the Owner
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents