Q 70

Please indicate the proper sequence of the acquisition cycle:?1. Approval of items for payment.?2. Authorized requisition for goods or services.?3. Cash disbursements.?4. Receipt of goods and services.?5. Authorized purchase of goods or services. A) 2, 5, 4, 1, 3 B) 2, 4, 5, 1, 3 C) 2, 1, 4, 5, 3 D) 2, 5, 1, 4, 3

Multiple Choice