Solved

If the Project Team and Organizational Officials Reassess the Project

Question 62

Multiple Choice

If the project team and organizational officials reassess the project after each subsequent SDLC phase to determine if the business conditions have changed or if a more detailed understanding of a system's costs,benefits,and risks suggest that the project is not as worthy as previously thought,they are:


A) adhering to the incremental commitment principle
B) overly cautious
C) using a CASE methodology
D) adhering to a bottom-up commitment principle

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents