A critical path is:

A critical path is:


A) a sequence of activities whose order and durations indirectly affect the completion date of a project
B) a sequence of activities whose order and durations directly affect the completion date of a project
C) a sequence of activities whose order must be performed in parallel
D) a sequence of activities whose duration cannot last more than 40 percent of the time allotted to the project