A predecessor is a
A) task that must happen at the same time as another task.
B) resource that must be used before another resource.
C) task that must happen before another task.
D) task that must happen after another task.
E) view in MS Project.
Correct Answer:
Verified
Q18: You can create subtasks within the tasks
Q19: When you create subtasks, the tasks associated
Q20: The resource sheet allows you to enter
Q21: MS Project is a sophisticated relational _
Q22: Subtasks are created and undone using the
Q24: In the resource view you see _
Q25: Task duration times are based on the
Q26: MS Project allows a project manager to
Q27: Why is MS Project considered a full-service
Q28: Dependencies are reflected in the _ screen.