Assume you are sequencing jobs using Johnson's rule.There are three jobs called A, B and C.The first step in assembling and the second step is painting. Job A requires 3 hours to assemble and 6 hours to paint.Job B requires 7 hours to assemble and 2 hours to paint.Job C requires 4 hours to assemble and 1 hour to paint.The objective is to minimize the total processing time of all jobs, using Johnson's rule.What is the correct sequence to process the jobs?
A) A - C - B
B) B - C - A
C) B - A - C
D) A - B - C
E) C - B - A
Correct Answer:
Verified
Q51: Which of the following priority rule will
Q55: Assume there are five jobs (i.e., A,
Q81: A job has 10 days of processing
Q82: Which of the following is a priority
Q83: Which of the following is not a
Q85: Which of the following priority rules used
Q96: A job has 5 days of processing
Q105: Which of the following is a principle
Q108: Assume you are sequencing jobs using Johnson's
Q112: Which of the following is a tool
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents