The internal project sponsor is frustrated by a lack of concise, regular updates regarding the status of a project. Which of the following changes would BEST satisfy the project sponsor?
A) Add the project sponsor to all project email correspondence moving forward
B) Include the project sponsor in all project meetings moving forward
C) Add a new line to the communications plan to provide a weekly status report with a dashboard
D) Include the project sponsor in the daily stand-up with the entire project team
Correct Answer:
Verified
Q473: A project's stakeholders have not been informed
Q474: A project manager is collecting the number
Q475: During a CCB, a SME evaluated the
Q476: Which of the following represents the order
Q477: A project sponsor approaches the project manager
Q479: A project needs two more months of
Q480: The PMO is confused by an entry
Q481: A project team is spread between two
Q482: During a project, a key stakeholder asks
Q483: In which of the following categories does
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents