A project sponsor approved an undocumented change without following the formal change control process. The resulting change caused an outage in a crucial accounting application. Which of the following change control processes would help mitigate the realization of this risk?
A) Regression plan
B) Quality plan
C) Change validation
D) Application version control
Correct Answer:
Verified
Q325: While planning a project, the project team
Q326: A project sponsor wants to know which
Q327: Which of the following project roles is
Q328: An organization is divided into three separate
Q329: A stakeholder wants to add four more
Q331: A project manager has updated the risk
Q332: Midway through a project, the building the
Q333: A financial audit is being performed on
Q334: A project team has just finished one
Q335: A project manager is implementing a new
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents