Task A starts on Day 1 and has a duration of two days. Task B has a duration of two days and starts on Day 3. Task C starts after Task A and has a duration of three days. Task D starts after Task B and Task C and has a duration of one day. Which of the following represents the critical path?
A) Five days
B) Six days
C) Seven days
D) Eight days
Correct Answer:
Verified
Q294: A company engaged a third-party audit firm
Q295: Based on the table below:
Q296: Which of the following is the MOST
Q297: A customer has requested a new feature
Q298: Which of the following are MOST likely
Q300: Which of the following documents will provide
Q301: Which of the following tasks are responsibilities
Q302: Which of the following are the roles
Q303: Ann, a project manager, is working for
Q304: A project manager is assigned a project
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents