A project manager is creating the monthly report for top management. The project manager has collected the information below: AC = 100 PV = 80 EV = 120 Based on this information, the CPI reflects which of the following about the project?
A) It is under budget.
B) It is over budget.
C) It is ahead of schedule.
D) It is behind schedule.
Correct Answer:
Verified
Q224: A company has hired a new project
Q225: A project team has determined it will
Q226: A project manager has identified a minor
Q227: A project manager is trying to explain
Q228: When forming a project team, there are
Q230: Which of the following is an example
Q231: The project team is distributed throughout a
Q232: A project manager has received a change
Q233: Two team members approach a project manager
Q234: A team member was assigned a new
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents