During an Ad-Hoc Meeting, the PM Notifies the Sponsor That

Question 182

Multiple Choice

During an ad-hoc meeting, the PM notifies the sponsor that while the project is on schedule, material costs have increased and the project is over budget. To save the project, the PM request a material contract with a less expensive vendor. The sponsor approves the change, and project comes in within target tolerances. The company, however, receives numerous stakeholder complaints. Which of the following is the MOST likely cause of these complaints?


A) The quality of the deliverable decreased due to the rising material cost.
B) The PM did not follow the project communication plan.
C) Quality assurance actions were not adjusted for the vendor change.
D) The change was not documented and approved.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents