Tasks B and D start after Task A is completed. Task C starts after Tasks B and D are completed. task E starts after Task D is completed. Task H starts after task B is completed. Task G starts after Tasks C and H are completed. Task F starts after Task E is completed. Following are the durations of all tasks: Which of the following tasks are on the critical path?
A) A, D, C, G
B) A, B, H, G
C) A, D, E, F
D) A, B, C, G
Correct Answer:
Verified
Q148: Which of the following documents serves the
Q149: A project team has completed a major
Q150: A project team completed a brainstorming activity
Q151: A Chief Executive Officer (CEO) has approached
Q152: A senior developer abruptly resigned without notice.
Q154: A contract review meeting has been scheduled
Q155: At a project kickoff meeting, several team
Q156: Which of the following information does the
Q157: A project encountered a problem and reached
Q158: Which of the following conflict resolution techniques
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents