A PM receives notification that an issue will impact a deliverable on the critical path. The issue is logged with a unique ID and assigned to a team member; however, the team member has not addressed it after a week. Which of the following would be the BEST approach to resolving the issue?
A) Assign a different team member to resolve the issue before the next status meeting.
B) Review the issue with the assigned team member to determine a due date.
C) Set a due date to resolve the issue and inform the assigned team member.
D) Report the team member to a functional manager for disciplinary action.
Correct Answer:
Verified
Q114: A daily standup Scrum meeting is BEST
Q115: Ann, one of the affected stakeholders, feels
Q116: Team members have reported poor sound quality
Q117: A risk with a high probability and
Q118: The project manager is reviewing the earned
Q120: When an action is taken on a
Q121: Which of the following is used to
Q122: A project manager at a projectized organization
Q123: A project team is defining detailed risks.
Q124: A client has provided a list of
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents