A PM Receives Notification That an Issue Will Impact a Deliverable

Question 119

Multiple Choice

A PM receives notification that an issue will impact a deliverable on the critical path. The issue is logged with a unique ID and assigned to a team member; however, the team member has not addressed it after a week. Which of the following would be the BEST approach to resolving the issue?


A) Assign a different team member to resolve the issue before the next status meeting.
B) Review the issue with the assigned team member to determine a due date.
C) Set a due date to resolve the issue and inform the assigned team member.
D) Report the team member to a functional manager for disciplinary action.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents