Solved

A Team Member Learns That an Assigned Task Is Not

Question 66

Multiple Choice

A team member learns that an assigned task is not due until the very end of the project. Moreover, the team member is not aware of any predecessor tasks dependent on completing the assigned task. Which of the following does the project manager use to decide if the team member can start the task later or earlier?


A) Review the PERT chart and evaluate if the task is a critical dependency.
B) Review the PERT chart and evaluate if the task is a discretionary dependency.
C) Review the PERT chart and evaluate if the task is a real dependency.
D) Review the PERT chart and evaluate if the task is an external dependency.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents