Solved

A Carpenter on a Project Team Reports There Is Insufficient

Question 5

Multiple Choice

A carpenter on a project team reports there is insufficient time to accomplish tasks on schedule. Which of the following is the FIRST step the project manager should take?


A) Assess the risk register's new items.
B) Review the task start and finish dates.
C) Obtain additional resources.
D) Analyze the assigned hours.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents