A Technician Needs to Make Changes to a Production System

Question 378

Multiple Choice

A technician needs to make changes to a production system. Before doing so, which of the following should be completed in case the changes have unintended consequences beyond their original scope?


A) Draft a complete scope of the changes.
B) Formulate a back-out plan for the changes.
C) Ensure all relevant end users are notified of the changes.
D) Create a risk analysis involving the changes.

Correct Answer:

verifed

Verified