A Technician Is Working on a Virtual Server Migration Project

Question 114

Multiple Choice

A technician is working on a virtual server migration project. The technician has already completed the SOW; however, the servers will not work without a critical network configuration that was missed in the original SOW. The technician needs to make the adjustments quickly. Which of the following best practice processes should the technician perform NEXT?


A) Obtain end-user acceptance for the proposed changes and submit a change plan for additional work.
B) Submit the changes to the change board for approval.
C) Notify the change team of the changes needed and perform the changes.
D) Escalate to stakeholders and obtain override approval for out-of-scope changes.
E) Document the changes and perform the work.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents