During the Initiating a Project Process, Which Product Is Updated

Question 71

Multiple Choice

During the Initiating a Project process, which product is updated to incorporate the estimated time and costs from the Project Plan?


A) Project Product Description
B) Business Case
C) Project Brief
D) Project mandate