For the Development Team and the Scrum Master, the Daily

Question 61

Multiple Choice

For the Development Team and the Scrum Master, the Daily Scrum is mandatory. Other roles may only participate without speaking. What is the most important reason that other roles are not allowed to speak?


A) Because it is not a status meeting for all stockholders.
B) Because other people speaking would let the meeting run late.
C) Because the meeting is just for updating the work done.

Correct Answer:

verifed

Verified