A story was estimated at eight ideal hours. A working day is eight hours. Developers can get about six hours of work done on a daily basis. What is the elapsed time required to complete the story?
A) 1.25 days
B) 1.33 days
C) 2 days
D) This cannot be determined without knowing the velocity.