Which of the following is a project planning methodology that involves a complex series of required simulations to provide information about schedule risk?
A) Monte Carlo Analysis.
B) Project Management Information System (PMIS)
C) Earned Value Management (EVM) .
D) Integrated Project Plan.
Correct Answer: