You are the Test Manager on a project following an iterative life-cycle model. The project should consist of nine iterations of one month duration each. It is planned to develop the most important features to have a stable core of the application in the first three iterations and to add the additional features in the last six iterations. At the beginning of the first iteration, only a draft version of the requirements specification document for the core features is available. Assume that during each of the first three iterations, the chosen features are fully completed and unit tested. Which of the following statements is true in this context?
A) The system test phase should start when all the requirements are frozen.
B) You should allocate a large effort for system testing during the first three iterations.
C) You should allocate all the effort for the system test phase only in the last iteration.
D) You should apply the same test strategy as used in a sequential life cycle model.
Correct Answer:
Verified
Q21: You can count on well-written requirements, but
Q22: Assume you are the Test Manager for
Q23: The following is the unique "critical" quality
Q24: Assume you are managing the system testing
Q25: The following is the unique "critical" quality
Q27: Assume you are the Test Manager in
Q28: You are performing a quality risk analysis
Q29: Assume that the following test cases have
Q30: Which of the following statements represents the
Q31: Consider an agile team adopting Extreme Programming
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents