A project manager has stated that he wants 'secure and controlled access to documentation, as well as support for impact analysis and traceability in terms of version history'. What element of requirements management will offer this?
A) Change control
B) Configuration control
C) Configuration management
D) Software support
Correct Answer:
Verified
Q2: A business analyst is allocating elicited requirements
Q3: A business analyst working on a project
Q4: Spicer, an herbs and spices company, is
Q5: A project sponsor has been asked to
Q6: A business analyst is concerned that the
Q8: Why it is important to record the
Q9: A business analyst has interviewed project stakeholders
Q10: During his yearly appraisal, a member of
Q11: Poppy Pet Care Kennels offers short-term accommodation
Q12: A business analyst is in the process
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents