A project has been running at the Wield Engineering Company for six months. The requirements have been signed off and development is underway; however, the development team has hit a problem and cannot implement an approved requirement. The business analyst has been asked to discuss this with the requirement owner. Before booking a meeting with the owner, the business analyst decides to check whether there are more requirements affected by this technical limitation. What will help the business analyst discover other affected requirements?
A) Change control
B) Configuration control
C) Horizontal traceability
D) Vertical traceability
Correct Answer:
Verified
Q13: In order to understand the existing processes,
Q14: A business analyst has collected the following
Q15: At Tiny Toys Ltd, business analyst Sophie
Q16: An international travel operator has a customer
Q17: A set of requirements for a new
Q19: A project, which was initiated several months
Q20: Make Me A Star Productions runs an
Q21: A business analyst is working on a
Q22: In a requirements catalogue, a distinction is
Q23: Isamu is a business analyst working on
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents