Which products, identified when creating a product breakdown structure, should each have a corresponding entry in the Risk Register?
A) Those that have been completed, but have NOT been quality checked
B) Those that have been broken down into sub-products
C) Those to be created outside the scope of the project
D) Those dependent on more than one other product
Correct Answer:
Verified
Q104: Which enables the project's products and all
Q105: Which theme defines the accountability for realization
Q106: If Work Package tolerance is forecast to
Q107: Identify the missing words in the following
Q108: Where should the names of those who
Q110: Which should be funded from a change
Q111: Which statement applies to Stage Plans?
A) Always
Q112: A product can NOT be supplied to
Q113: Which is NOT a benefit of using
Q114: Which of the following take place before
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents