Which of the following is NOT a purpose of the Closing a Project process?
A) Plan the activities required to close a project
B) Enable a comparison of the original objectives of a project against what was actually achieved
C) Enable premature closure if the Project Board request that a project should no longer continue
D) Provide a fixed point at which acceptance for the project product is confirmed
Correct Answer:
Verified
Q18: Which is a responsibility of the managing
Q19: Which is a purpose of the Business
Q20: Which is a purpose of a Project
Q21: Which principle helps to define what should
Q22: Which is a purpose of the Plans
Q24: Which is a responsibility of a risk
Q25: Which theme provides the controls to escalate
Q26: What process is used by the Project
Q27: Which is a difference between management and
Q28: Which of the following statements about the
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents