The following data relate to direct materials costs for February:
Materials cost per yard: standard, $2.00; actual, $2.10
Standard yards per unit: standard, 4.5 yards; actual, 4.75 yards
Units of production: 9,500
Calculate the direct materials quantity variance.
A) $4,512.50 unfavorable
B) $4,512.50 favorable
C) $4,750.00 unfavorable
D) $4,750.00 favorable
Correct Answer:
Verified
Q81: The following data is given for the
Q82: The following data relate to direct materials
Q83: The formula to the compute direct labor
Q83: The following data relate to direct labor
Q85: The standard costs and actual costs for
Q87: The following data relate to direct labor
Q88: The following data is given for the
Q89: The following data relate to direct labor
Q90: The following data relate to direct labor
Q91: The standard costs and actual costs for
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents