The following data relate to direct materials costs for February:
Materials cost per yard: standard, $2.00; actual, $2.10
Standard yards per unit: standard, 4.5 yards; actual, 4.75 yards
Units of production: 9,500
Calculate the total direct materials cost variance.
A) $9,262.50 unfavorable
B) $9,262.50 favorable
C) $3,780.00 unfavorable
D) $3,562.50 favorable
Correct Answer:
Verified
Q88: The following data is given for the
Q89: The following data relate to direct labor
Q90: The following data relate to direct labor
Q91: The standard costs and actual costs for
Q91: Which of the following is not a
Q92: The following data relate to direct labor
Q95: The following data relate to direct labor
Q96: The following data relate to direct labor
Q97: The Flapjack Corporation had 8,200 actual direct
Q98: The following data relate to direct labor
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents