A job takes 156 hours to finish. Using an 8-hour workday, in how many days and hours is the job finished?
A) 19 days 4 hours
B) 20 days 2 hours
C) 21 days 6 hours
D) 22 days
Correct Answer:
Verified
Q1: Distance = speed x _.
Q2: The _ system means that each job
Q3: An assembly job takes 15 minutes. How
Q4: Express 0.45 hour in minutes.
A) 24
B) 25
C)
Q5: Flat-rate times are given in hours and
Q6: An airplane travels at a speed of
Q7: Knot means nautical miles per hour. One
Q8: A boat travels at a land speed
Q10: A mechanic works on a differential overhaul.