A Company Is Considering a Project in Which the Risk

Question 49

Multiple Choice

A company is considering a project in which the risk associated with annual cash flows varies considerably from year to year.  Which of the following methods will best allow management to include consideration of risk in the analysis?


A) Pure play method
B) Accounting beta method
C) Certainty approach method
D) Overlay approach