If a Party's Principal Reason for a Contract Is Substantially

Question 67

Multiple Choice

If a party's principal reason for a contract is substantially impaired without his fault by the occurrence of an unexpected event, that party's remaining duties to render performance are discharged due to the doctrine of:


A) frustration of purpose
B) subjective impossibility
C) objective impossibility
D) commercial impracticability

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge