Restore Inc. contracts to resurface the pools at Swim Park by June 1. Restore knows that if performance is not timely, Swim Park will have to delay its seasonal opening. Restore finishes the job June 15. In a suit for breach, Swim Park can recover
A) the cost of new pools.
B) the difference between the contract and market prices for the work.
C) the loss of profit from the delayed opening.
D) nothing-the work is done.
Correct Answer:
Verified
Q53: Berry Farm hires Chun to repair its
Q54: Renew Turf Inc. enters into a contract
Q55: Cow's Milk LLC needs a certain part
Q56: Dory enters into a contract with Eton
Q57: Len contracts to work for Media Corporation
Q59: Copper Wire Inc. and Direct Electric LLC
Q60: Ochre holds one ton of perishable fruit
Q61: Jet enters into a contract to buy
Q62: Max orally agrees to construct two outbuildings
Q63: Home Furnishing Store's contract for a sale
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents