A PERT network consists of activities linked by arrows. Suppose two of the activities on the network are labeled "A" and "B." An arrow from "A" to "B" indicates that
A) the same resources used to complete "A" are also used to complete "B."
B) "A" and "B" can be completed at the same time.
C) "A" takes longer to complete than "B."
D) "A" must be completed before "B" can begin.
Correct Answer:
Verified
Q304: Sparky knows that installing the new equipment
Q305: Both PERT diagrams and Gantt charts are
Q306: PERT is a popular control method used
Q307: What are the ISO 9001 and ISO
Q308: How are MRP and ERP similar? How
Q310: One of Sparky's goals is to expand
Q311: While planning a new product launch, Cassandra
Q312: The purpose of determining the critical path
Q313: The first step in the development of
Q314: The arrangements Minimotors has worked out with
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents