A project will cost $1,000 initially, and is expected to return $500 in year 1, $400 in year 2, $300 in year 3, $100 in year 4, and nothing thereafter. What is the project's NPV if the appropriate
Cost of capital is 10%? Round your answer to the nearest dollar.
A) +$182
B) +$79
C) +$1,079
D) none of the above
Correct Answer:
Verified