Which of the following is not one of the network rules for PERT/CPM?
A) Networks can start and finish at multiple events.
B) Identify each unique activity within a project by a capital letter that corresponds only to that activity.
C) Branch direction indicates the general progression in time from left to right.
D) When a number of activities end at one event, no activity starting at that event may begin before all activities ending at that event are complete.
E) Two or more activities cannot share graphically the same beginning and ending events.
Correct Answer:
Verified
Q42: According to Ohno and Toyota, _ is
Q43: _ is a technique used to examine
Q44: Users apply _ to projects where there
Q45: According to Ohno and Toyota, _ is
Q46: _ is a tool that reduces processes
Q48: According to Ohno and Toyota, _ is
Q49: In a PERT network, a/an _ is
Q50: A/An _ consists of activities or steps
Q51: According to Ohno and Toyota, _ is
Q52: _ techniques are primarily applied to existing
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents