To determine the number of cubic yards of concrete needed for a job, find the number of cubic feet and divide by ____.
A) 3
B) 9
C) 12
D) 27
Correct Answer:
Verified
Q18: In tropical climates, footings must be placed
Q19: Rise is the vertical distance of a
Q20: The _ for a foundation provides a
Q21: _ tests are made by inspectors on
Q22: A rigid foam forming system called insulated
Q24: Metric rebars are measured in _.
A) millimeters
B)
Q25: If concrete is moist-cured for 7 days,
Q26: Protect concrete from freezing for a minimum
Q27: Steel reinforcing bars, called rebars, are used
Q28: _ strength is the quality of being