Question 52

Multiple Choice

Calculate the forecasted cost at completion if the total budgeted cost = R100 000, the CEV is R80 000, and the CAC is R40 000.


A) FCAC = R50 000
B) FCAC = R200 000
C) FCAC = R60 000
D) FCAC = R40 000