The following table contains information about five jobs waiting to be processed at work center number three.
Using the EDD rule, the sequence of jobs would be
A) d-e-b-a-c.
B) a-d-c-b-e.
C) e-d-b-a-c.
D) a-d-c-e-d.
E) e-b-c-d-a.
Correct Answer:
Verified